Harald asked for help in mapping Milestones to Promoted builds. The map is implicit in the 3.1 Build Schedule and in the list of Promoted Builds, but the explicit map is:

• Milestone 7 - Build 30 (target date 11/23)
• Milestone 6 - Build 26 (target date 10/26)
• Milestone 5 - Build 20 (target date 9/14)
• Milestone 4 - Build 16
• Milestone 3 - Build 10
• Milestone 2 - Build 6
• Milestone 1 - Build 2

The functionality of promoted builds is cumulative. People should try using the latest promoted build; if that shows a regression, try the latest build that corresponds to a milestone... and file a bug.

Remember that all these are bleeding edge builds. If you are interested in stable builds you should use either 3.0.1 or 2.1.1, either the GlassFish Server Open Source Edition or the Oracle GlassFish Server (also see GlassFishForBusiness).