Iterative and Incremental Principle Series 4: Iteration Planning – (a.k.a What should I do today?)

Welcome back to the fourth of a five part series on applying the Iteration and Incremental principle.  During the last segment, we discussed how the Implementation Plan includes the number of the iterations for a project, but not the specifics about what will occur during each iteration.  Today, we will explore Iteration Planning and discuss how and when to plan your iterations.

As mentioned yesterday, OUM prescribes initially planning your project approach at a high level by creating an Implementation Plan.  As the project moves through the lifecycle, the plan is progressively refined.  Specifically, the details of each iteration is planned prior to the iteration start.

The Iteration Plan starts by identifying the iteration goal.  An example of an iteration goal during the OUM Elaboration Phase may be to complete the RD.140.2 Create Requirements Specification for a specific set of requirements.  Another project may determine that their iteration goal is to focus on a smaller set of requirements, but to complete both the RD.140.2 Create Requirements Specification and the AN.100.1 Prepare Analysis Specification. 

In an OUM project, the Iteration Plan needs to identify both the iteration goal – how far along the implementation lifecycle you plan to be, and the scope of work for the iteration.  Since each iteration typically ranges from 2 weeks to 6 weeks, it is important to identify a scope of work that is achievable, yet challenging, given the iteration goal and timeframe. 

OUM provides specific guidelines and techniques to help prioritize the scope of work based on criteria such as risk, complexity, customer priority and dependency.  In OUM, this prioritization helps focus early iterations on the high risk, architecturally significant items helping to mitigate overall project risk. 

Central to the prioritization is the MoSCoW (Must Have, Should Have, Could Have, and Won’t Have) list.   The result of the MoSCoW prioritization is an Iteration Group.  This is a scope of work to be worked on as a group during one or more iterations. 

As I mentioned during yesterday’s blog, it is pointless to plan my daily exercise in advance since several factors, including the weather, influence what exercise I perform each day.  Therefore, every morning I perform Iteration Planning.   My “Iteration Plan” includes the type of exercise for the day (run, bike, elliptical), whether I will exercise outside or at the gym, and how many interval sets I plan to complete.   

I use several factors to prioritize the type of exercise that I perform each day.  Since running outside is my highest priority, I try to complete it early in the week to minimize the risk of not meeting my overall goal of doing it twice each week.  Regardless of the specific exercise I select, I follow the guidelines in my Implementation Plan by applying the 6-minute interval sets.  Just as in OUM, the iteration goal should be in context of the overall Implementation Plan, and the iteration goal should move the project closer to achieving the phase milestone goals.

Having an Implementation Plan details the strategy of what I plan to do and keeps me on track, while the Iteration Plan affords me the flexibility to juggle what I do each day based on external influences thus maximizing my overall success.

Tomorrow I’ll conclude the series on applying the Iterative and Incremental approach by discussing how to manage the iteration duration and highlighting some benefits of applying this principle.

Wednesday Sep 26, 2012

Iterative and Incremental Principle Series 3: The Implementation Plan (a.k.a The Fitness Plan)

Welcome back to the Iterative and Incremental Blog series.  Yesterday, I demonstrated how shorter interval sets allowed me to focus on my fitness goals and achieve success.  Likewise, in a project setting, shorter milestones allow the project team to maintain focus and experience a sense of accomplishment throughout the project lifecycle.  Today, I will discuss project planning and how to effectively plan your iterations.

Admittedly, there is more to applying the iterative and incremental principle than breaking long durations into multiple, shorter ones.  In order to effectively apply the iterative and incremental approach, one should start by creating an implementation plan.  

In a project setting, the Implementation Plan is a high level plan that focuses on milestones, objectives, and the number of iterations.  It is the plan that is typically developed at the start of an engagement identifying the project phases and milestones. 

When the iterative and incremental principle is applied, the Implementation Plan also identified the number of iterations planned for each phase.  The implementation plan does not include the detailed plan for the iterations, as this detail is determined prior to each iteration start during Iteration Planning.  An individual iteration plan is created for each project iteration.

For my fitness regime, I also created an “Implementation Plan” for my weekly exercise.   My high level plan included exercising 6 days a week, and since I cross train, trying not to repeat the same exercise two days in a row.  Because running on the hills outside is the most difficult and consequently, the most effective exercise, my implementation plan includes running outside at least 2 times a week.   Regardless of the exercise selected, I always apply a series of 6-minute interval sets.

 I never plan what I will do each day in advance because there are too many changing factors that need to be considered before that level of detail is determined.  If my Implementation Plan included details on the exercise I was to perform each day of the week, it is quite certain that I would be unable to follow my plan to that level.  It is unrealistic to plan each day of the week without considering the unique circumstances at that time.  For example, what is the weather?  Are there are conflicting schedule commitments?  Are there injuries that need to be considered?  Likewise, in a project setting, it is best to plan for the iteration details prior to its start.

Join me for tomorrow’s blog where I will discuss when and how to plan the details of your iterations.

Monday Mar 19, 2012

Developing an Implementation Plan with Iterations by Russ Pitts

Developing an Implementation Plan with Iterations by Russ Pitts 

Ok, so you have come to grips with understanding that applying the iterative concept, as defined by OUM is simply breaking up the project effort you have estimated for each phase into one or more six week calendar duration blocks of work.

Idea being the business user(s) or key recipient(s) of work product(s) being developed never go longer than six weeks without having some sort of review or prototyping of the work results for an iteration…”think-a-little”, “do-a-little”, and “show-a-little” in a six week or less timeframe…ideally the business user(s) or key recipients(s) are involved throughout.

 

You also understand the OUM concept that you only plan for that which you have knowledge of. The concept further defined, a project plan initially is developed at a high-level, and becomes more detailed as project knowledge grows. Agreeing to this concept means you also have to admit to the fallacy that one can plan with precision beyond six weeks into a project…Anything beyond six weeks is a best guess in most cases when dealing with software implementation projects.

 

Project planning, as defined by OUM begins with the Implementation Plan view, which is a very high-level perspective of the effort estimated for each of the five OUM phases, as well as the number of iterations within each phase.

 

You might wonder how can you predict the number of iterations for each phase at this early point in the project. Remember project planning is not an exact science, and initially is high-level and abstract in nature, and then becomes more detailed and precise as the project proceeds.

 

So where do you start in defining iterations for each phase for a project?

 

The following are three easy steps to initially define the number of iterations for each phase:

 

Step 1 => Start with identifying the known factors…

 

…Prior to starting a project you should know:

 

 <!--[if !supportLists]-->· <!--[endif]-->The agreed upon time-period for an iteration (e.g 6 weeks, or 4 weeks, or…) within a phase (recommend keeping iteration time-period consistent within a phase, if not for the entire project)

 

<!--[if !supportLists]-->· <!--[endif]-->The number of resources available for the project

 

<!--[if !supportLists]-->· <!--[endif]-->The number of total number of man-day (effort) you have estimated for each of the five OUM phases of the project

 

<!--[if !supportLists]-->· <!--[endif]-->The number of work days for a week

 

Step 2 => Calculate the man-days of effort required for an iteration within a phase…

 

Lets assume for the sake of this example there are 10 project resources, and you have estimated 2,536 man-days of work effort which will need to occur for the elaboration phase of the project. Let’s also assume a week for this project is defined as 5 business days, and that each iteration in the elaboration phase will last a calendar duration of 6 weeks. A simple calculation is performed to calculate the daily burn rate for a single iteration, which produces a result of…

 

((Number of resources * days per week) * duration of iteration) = Number of days required per iteration

 

((10 resources * 5 days/week) * 6 weeks) = 300 man days of effort required per iteration

 

 

Step 3 => Calculate the number of iterations that can occur within a phase

 

Next calculate the number of iterations that can occur for the amount of man-days of effort estimated for the phase being considered…

 

(number of man-days of effort estimated / number of man-days required per iteration) = # of iterations for phase

 

(2,536 man-days of estimated effort for phase / 300 man days of effort required per iteration) = 8.45 iterations, which should be rounded to a whole number such as 9 iterations*

 

*Note - It is important to note this is an approximate calculation, not an exact science. This particular example is a simple one, which assumes all resources are utilized throughout the phase, including tech resources, etc. (rounding down or up to a whole number based on project factor considerations). It is also best in many cases to round up to higher number, as this provides some calendar scheduling contingency.

 

About

OUM Logo
The Oracle® Unified Method (OUM) is Oracle’s standards-based method that enables the entire Enterprise Information Technology (IT) lifecycle.

Read:

· Brief

· White Paper

· Customer Program Data Sheet

Connect:

· OUM on Twitter

· OUM on LinkedIn

Search

Archives
« April 2014
SunMonTueWedThuFriSat
  
1
2
3
4
5
6
7
8
9
10
11
12
13
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
   
       
Today
Feeds